Determinants of Successful Implementation of Government Affordable Housing Projects in Nyanza Region, Kenya

Gudah John

Click an author's name to view their details

Gudah John Corresponding Author

BUSINESS MANAGEMENT, MAASAI MARA UNIVERSITY, KENYA

Correspondence: gudahjohn@gmail.com

Received
02 Jul 2026
Published
10 Aug 2026

Abstract

Affordable housing has become a critical development priority in Kenya due to persistent housing deficits, rapid urbanization, and increasing pressure on infrastructure systems. Despite government efforts through the Affordable Housing Programme (AHP), implementation outcomes remain uneven across regions. In Nyanza Region, significant disparities exist in project delivery, with Kisumu County accounting for 40.7% of housing units while Homa Bay contributes only 5.6%, indicating unequal implementation performance across counties. This study therefore examined the determinants of successful implementation of government affordable housing projects in Nyanza Region, Kenya. The study was anchored on Project Management Theory and Systems Theory and adopted a descriptive and explanatory research design. The target population comprised 18 affordable housing projects with a total of over 10,327 housing units. Census sampling was used due to the small and accessible population. Secondary data was collected from official housing project records. Data were analyzed using descriptive statistics, Pearson correlation, and multiple regression analysis to examine the relationship between project implementation determinants (top management support, political support, and contractor technical competence) and project success. The findings revealed a strong positive and statistically significant relationship between project implementation determinants and successful project implementation (r = 0.742, p = 0.000). Regression results further showed that project implementation determinants explain 55.1% of the variation in project success (R² = 0.551), while the overall model was statistically significant (F = 19.600, p = 0.000). The coefficient analysis indicated that project implementation determinants had a significant positive effect on project success (β = 0.742, p = 0.000), implying that improvements in managerial support, political backing, and contractor competence significantly enhance project implementation outcomes. The study concludes that successful implementation of affordable housing projects in Nyanza Region is strongly influenced by managerial, political, and technical factors. It recommends strengthening top management support, improving contractor capacity, and enhancing coordination between national and county governments to improve project delivery effectiveness.

Keywords: Affordable Housing, Project Implementation, Contractor Competence, Political Support, Top Management Support, Nyanza Region, Kenya.

How to Cite

APA

John, G. (2026). Determinants of Successful Implementation of Government Affordable Housing Projects in Nyanza Region, Kenya. Journal of Contemporary Academic Research and Methodologies, 1(6). https://doi.org/10.5281/zenodo.21858396

MLA

John, Gudah. "Determinants of Successful Implementation of Government Affordable Housing Projects in Nyanza Region, Kenya." Journal of Contemporary Academic Research and Methodologies, vol. 1, no. 6, 2026. DOI: https://doi.org/10.5281/zenodo.21858396

Chicago

John, Gudah. "Determinants of Successful Implementation of Government Affordable Housing Projects in Nyanza Region, Kenya." Journal of Contemporary Academic Research and Methodologies 1, no. 6 (2026). https://doi.org/10.5281/zenodo.21858396

References

Aibinu, A. A., & Odeyinka, H. A. (2020). Construction delays and their causative factors in developing countries. International Journal of Project Management, 38(2), 105–118. https://doi.org/10.1016/j.ijproman.2019.09.001 Aje, I. O., Odusami, K. T., & Ogunsemi, D. R. (2022). Contractor competence and construction project performance in Nigeria. Journal of Construction in Developing Countries, 27(1), 1–18. https://doi.org/10.21315/jcdc2022.27.1.1 Creswell, J. W., & Creswell, J. D. (2018). Research design: Qualitative, quantitative, and mixed methods approaches (5th ed.). SAGE Publications. Damoah, I. S., Ayagre, P., & Takieddine, A. (2021). Political interference and public project performance in Ghana. Public Administration and Development, 41(3), 145–158. https://doi.org/10.1002/pad.1912 Field, A. (2018). Discovering statistics using IBM SPSS statistics (5th ed.). SAGE Publications. Flyvbjerg, B. (2018). The iron law of megaproject management. Project Management Journal, 49(6), 3–18. https://doi.org/10.1177/8756972818800961 Government of Kenya. (2023). Affordable housing programme implementation report. Government Printer. Heizer, J., Render, B., & Munson, C. (2020). Operations management: Sustainability and supply chain management. Pearson. Irungu, C., Mwangi, P., & Wanjohi, S. (2022). Contractor capacity and infrastructure project performance in Kenya. African Journal of Construction Economics and Management, 11(2), 45–60. https://doi.org/10.1080/23311916.2022.2034567 Joslin, R., & Müller, R. (2020). Relationships between project governance and project success. International Journal of Project Management, 38(2), 93–103. https://doi.org/10.1016/j.ijproman.2019.09.002 Kerzner, H. (2022). Project management: A systems approach to planning, scheduling, and controlling (13th ed.). Wiley. Love, P. E. D., Edwards, D. J., & Irani, Z. (2021). Rework in construction projects: Causes and consequences. Engineering, Construction and Architectural Management, 28(4), 1123–1142. https://doi.org/10.1108/ECAM-03-2020-0205 Mwangi, J. (2023). Determinants of housing project implementation in Kenya. Journal of African Development Studies, 15(1), 67–82. https://doi.org/10.4314/jads.v15i1.5 Nguyen, L. D., Chileshe, N., & Rameezdeen, R. (2022). Contractor capability and construction project performance in developing countries. International Journal of Construction Management, 22(5), 1–15. https://doi.org/10.1080/15623599.2021.1881952 Ofori, G. (2020). Construction industry and housing delivery in developing countries. Construction Management and Economics, 38(1), 1–17. https://doi.org/10.1080/01446193.2019.1695423 Olawale, Y. A., & Sun, M. (2020). Construction project risk management in South Africa. Journal of Financial Management of Property and Construction, 25(3), 341–356. https://doi.org/10.1108/JFMPC-06-2019-0045 Osei-Kyei, R., & Chan, A. P. C. (2021). Review of public-private partnership infrastructure projects. International Journal of Project Management, 39(3), 123–135. https://doi.org/10.1016/j.ijproman.2020.09.004 PMI (Project Management Institute). (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.). PMI. Sambasivan, M., & Soon, Y. W. (2020). Causes and effects of delays in infrastructure projects. International Journal of Project Management, 38(1), 18–29. https://doi.org/10.1016/j.ijproman.2019.11.001 Turner, J. R. (2022). The handbook of project-based management (5th ed.). McGraw-Hill. UNDP. (2022). Human development report: Housing and urban development challenges. United Nations Development Programme. World Bank. (2023). Global housing deficit and urban development report. World Bank Publications. https://doi.org/10.1596/978-1-4648-1950-0 Zwikael, O., & Smyrk, J. (2021). Project governance and management support. International Journal of Managing Projects in Business, 14(4), 1–20. https://doi.org/10.1108/IJMPB-03-2020-0102
CC BY-NC-SA 4.0

This article is published under the Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License. Free to read, share, and adapt with attribution.

Article Access
↓ Download PDF
67
Views
35
Downloads
Metadata
ISSN 3139-7247
Tracking ID JCARM_JUL_26_012
Article No. 001
↓ Download JATS XML
Article Info
Journal JCARM
Volume Vol 1, No 6
Year 2026
Type Original Research Article
Licence CC BY-NC-SA 4.0
Share